February 06 2025 13:08:32     The first phase of Shaanxi BDO was stopped in early August 2024, and the restart time was not determined; the second phase was running stably.
Shaanxi Guorong 60,000 tons/year BDO device was stopped in mid-April 2024, and the restart time is not yet determined.
The third phase of the BDO device of Xinjiang Meike Chemical was stopped, and the first phase 24 device was operating normally.
Xinjiang Tianye's 210,000 tons/annual capacity BDO devices were all stopped at the end of September, and the restart time was not determined.
Henan Energy Hebi Coal Chemical 100,000 tons/year BDO device, the entire factory was suspended for inspection on July 10, 2024, and the restart time is not yet determined.
Henan Kaixiang's 110,000-ton BDO device is operating stably, mainly supplying downstream PBT, PBAT and other self-use and contracts, with no quotation in spot stock.
Inner Mongolia Huaheng has three sets of 104,000 tons of BDO devices each. One of them is in the parking space and two sets of devices operate stably.
The 300,000-ton BDO device of the first phase of Dalian Hengli is being stopped; the 300,000-ton BDO device of the second phase of Dalian Hengli has produced qualified products, with a load of around 50%, mainly for self-use.
Sichuan Wanhua's annual output of 60,000 tons will be installed on December 10, 2024. The BDO and downstream products will be suspended for maintenance and will be restarted near January 10.
The load of two 3D units of Inner Mongolia 150,000 tons per year is 60-70%.
The load of the 300,000 tons/year BDO device in Inner Mongolia Junzheng has dropped to around 70%, and the downstream PTMEG is mainly used for self-use.
Area |
Device dynamics |
Shaanxi Shaanxi Chemical |
Phase I stopped in early August 2024, and the restart time has not been determined; Phase II operates stably |
Shaanxi Guorong |
The 60,000 tons/year BDO device was stopped in mid-April 2024, and the restart time is uncertain |
Xinjiang Meike |
The third phase device is stopped, and the first phase device is operated normally |
Xinjiang Tianye |
210,000 tons/annual capacity BDO device device is being parked |
Dalian Hengli |
Phase 1 is being parked, Phase 2 is running stably |
Henan Energy Chemical Industry |
The factory was suspended for major inspection on July 10, and the restart time was not yet determined |
Henan Kaixiang |
110,000 tons of BDO device operates stably, mainly supply downstream PBT, PBAT and other self-use and contracts, no quotation in spot stock |
Inner Mongolia Huaheng |
Three sets of 104,000 tons of BDO devices each, one of which is in the parking space, and two sets of devices operate stably |
Xinjiang Cathay Pacific |
One set of stable operation; one set of devices was repaired on December 14, 2024, and has been restarted and stable operation |
If you have any enquiries or purchasing needs, please feel free to contact SunSirs with support@sunsirs.com.
- 2025-02-21 SunSirs: The Domestic BDO Market Remained on the Sidelines on February 20th
- 2025-02-20 SunSirs: The Domestic BDO Market Remained on the Sidelines on February 18th
- 2025-02-19 SunSirs: The Domestic BDO Market Remained on the Sidelines on February 18th
- 2025-02-13 SunSirs: Some Domestic BDO Enterprises will be Repaired Soon on February 13
- 2025-02-12 SunSirs: The Domestic Butadiene Market Saw a Slight Decline on February 11th